Requirements Phase

Description
During the Requirements Analysis Phase, the business (project in-scope) requirements that were previously documented in an earlier phase are revalidated and further analyzed and decomposed into high-level system (functional and non-functional) requirements that define the automated system/application in more detail with regard to inputs, processes, outputs, and interfaces. If appropriate, a logical depiction of the data entities, relationships and attributes of the system/application is also created. During the Requirements Analysis Phase, the initial strategy for testing and implementation is also begun. In addition, the work planned for future phases is redefined, if necessary, based on information acquired during the Requirements Analysis Phase. The Requirements Analysis Phase ends with a review to determine readiness to proceed to the Design Phase.

Detailed application requirements (both functional and non-functional) are required to permit detailed project management planning, execution and control. If detailed requirements and subsequent planning identify a breach of the investment-level cost, schedule or performance baselines established at the end of the planning phase, a formal change to the Investment Baselines will be requested. The purpose of acquisition planning in the Requirements Analysis Phase is to allocate the requirements among development segments, research and apply lessons learned from previous projects, develop a schedule that lists activities for completion and work products to be produced with appropriate estimated completion dates, identify potential product and service providers, and award contracts.

Responsibilities
Project Manager: The Project Manager is responsible and accountable for the successful planning and execution of the Requirements Analysis Phase. The Project Manager is responsible for leading the Integrated Project Team that accomplishes the Phase tasks and deliverables.

Integrated Project Team: The Integrated Project Team members (regardless of the organization of permanent assignment) are responsible for accomplishing assigned tasks as directed by the Project Manager.

Contracting Officer: The Contracting Officer is responsible and accountable for preparing solicitation documents under the guidance of the Project Manager and Head of Contracting Activity.

Critical Partners: The Critical Partners provide oversight, advice and counsel to the Project Manager to ensure that the Requirements Document addresses relevant standards. Additionally, Critical Partners provide information, judgments, and recommendations during the Requirements Review.

Activities
The tasks described below are performed during the Requirements Analysis Phase:

The Acquisition Plan becomes critical after the Requirements Document has been approved. Several acquisitions may be needed to procure an entire system and are a continuous part of the life cycle. The Acquisition Plan is continuously updated with the active involvement of the Investment Manager and Contracting Officer.

Exit Criteria
Objective: To determine if the project requirements have been defined sufficiently to be translated into the Business Product.

Phase Specific Exit Criteria:

Generic Exit Criteria:

Project Review
The Requirements Review is conducted to verify that the requirements are complete, accurate, consistent and problem-free; to evaluate the responsiveness of the requirements to the business requirements; to ensure that the requirements are a suitable basis for subsequent design activities; to ensure traceability within the requirements and between the design documents; and to affirm final agreement regarding the content of the Requirements Document. Upon successful completion of this review, the Requirements Document is baselined.

Stage Gate Review
The Requirements Analysis Stage Gate Review considers whether the project should proceed to the Design Phase.